CLIENTS |
REFERENCES PROJETS |
ANNEES DE REALISATION |
MONTANT
DES
TRAVAUX |
SPECIFICITE |
USINES ET BATIMENTS INDUSTRIELS |
STE TNE DE SIDERURGIE |
ACIERIE D'EL FOULADH MENZEL BOURGUIBA |
1963/1964 |
312.000 DT |
GENIE CIVIL + V.R.D. |
SOGICOT |
USINE DE TISSAGE A KSAR HILAL ET MOKNINE |
1964/1966 |
877.000 DT |
GENIE CIVIL + V.R.D. |
ALKIMIA |
USINE T.P.P. - GABES |
1974/1977 |
1.200.000 DT |
GENIE CIVIL + V.R.D. |
I.C.M. |
USINE I.C.M. 2 - GABES |
1975/1976 |
1.300.000 DT |
GENIE CIVIL + V.R.D. |
I.C.F. |
USINE I.C.F. - GABES |
1975/1976 |
600.000 DT |
GENIE CIVIL + V.R.D. |
HEURTEY INDUSTRIE |
USINE M.A.P. - GABES |
1975/1976 |
500.000 DT |
GENIE CIVIL + V.R.D.
|
SEPA |
USINE SEPA 1 - GABES |
1977/1978 |
7.450.000 DT |
GENIE CIVIL + V.R.D. |
S E P A |
USINE SEPA 1 - GABES TRAVAUX MARITIME |
1978/1979 |
1.300.000 DT |
GENIE CIVIL + V.R.D. |
CREUSOT LOIRE |
USINE SEPA II - GABES |
1981/1984 |
6.700.000 DT |
GENIE CIVIL + V.R.D. |
STE GENERALE AUTOMATISME |
USINE I.C.M. 3 - GABES |
1981/1982 |
4.140.000 DT |
GENIE CIVIL + V.R.D. |
T.P.1 |
USINE DAP / NPK - GABES |
1984/1985 |
1.656.000 DT |
GENIE CIVIL + V.R.D. |
SOFAT |
USINE DE FAIENCERIE TEJEROUINE |
1985/1986 |
1.074.000 DT |
GENIE CIVIL + V.R.D. |
CMT |
MATEUR |
1983/1985 |
4.500.000 DT |
BAT. ADMIN 5000 M2 |
SACEM |
USINE DE MENZEL BOURGUIBA |
1985/1986 |
601.000 DT |
GENIE CIVIL + V.R.D. |
SAKMO |
USINE DE MOTEUR DIESEL SAKIET SIDI YOUSSEF |
1987/1988 |
2.546.000 DT |
GENIE CIVIL + V.R.D. |
SPCD |
USINE - MEGRINE |
1987/1988 |
1.079.000 DT |
GENIE CIVIL + V.R.D. |
MAGRIPLAST |
USINE - ARIANA |
1987/1988 |
830.000 DT |
GENIE CIVIL + V.R.D. |
STE FILIN |
USINE DE FILIATURE DE LIN FOUCHANA |
1991/1992 |
3.916.000 DT |
GENIE CIVIL + V.R.D. |
STE TISSAGE |
USINE DE TISSAGE KSAR SAID |
1991/1993 |
1.850.000 DT |
GENIE CIVIL + V.R.D. |
S.M.B. |
INSTALLATION MINIERE DE BOUGRINE |
1993 |
2.005.000 DT |
GENIE CIVIL + V.R.D. |
S.M.B. |
INSTALLATION MINIERE DE BOUGRINE LA GOULETTE |
1993/1994 |
2.328.848 DT |
PIEUX FORES + PALPLANCHES
GENIE CIVIL + V.R.D. |
ROUSSEL TUNISIE |
USINE ROUSSEL MEGRINE |
1995/1996 |
668.000 DT |
PIEUX FORES + PALPLANCHES
GENIE CIVIL + V.R.D. |
S. M. L. T |
DEPOT ARIANA + ATELIER D'ENTRETIENT ET
ELECTRIQUE SOUS-STATION |
1993/1997 |
14.000.000 DT |
EN GROUPEMENT AVEC
CACCAVALE. ATELIER
INDUSTRIELLE =22000m2 |
T.M.M.
GROUPE M'ZABI |
TANNERIE ET MAGISSERIE DE GROMBALIA |
1996/1997 |
3.000.000 DT |
GENIE CIVIL + V.R.D. |
G. M. G. |
LES GRANDS MOULINS DE GABES |
1997/1998 |
4.500.000 DT |
BATIMENT MINOTERIE ET
SEMOULERIE EXECUTION
EN COFFRAGE GLISSANT H = 37 m |
AL KIMIA |
EXTENSION USINE AL KIMIA A GABES |
1997/1998 |
1.600.000 DT |
BATIMENT INDUSTRIELLE |
SATUCO |
USINE CONDITIONNEMENT HUILES COMESTIBLES |
1999/2000 |
1.830.000 DT |
GENIE CIVIL + VRD |
GROUPE CHIMIQUE DE GABES |
PIEUX USINE SAEPA A GABES |
2003 |
330.000 DT |
PIEUX FORES |
SOTUVER |
CONSTRUCTION DE L'USINE SOTUVER |
2003/2004 |
8.200.000 DT |
GENIE CIVIL + VRD |
SOTUCHOC |
EXTENSION DE L'USINE ICT ( SOTUCHOC ) |
2003/2004 |
4.600.000 DT |
GENIE CIVIL + VRD |